How do you value an automation before funding it?
The short answer
To value an automation, add the value of hours saved, errors avoided and capacity gained, then subtract the total cost of software, setup, training and upkeep. Weekly hours saved, times the loaded hourly cost, times 52 is the yearly time value; add the yearly cost of the errors that stop. If the total barely beats the cost, choose another process.
Operations and AI Enablement · Reviewed by Bracey Skyway Partners, Buffalo, NY
Practice: Operations and AI Enablement
The formula
- Time value
- (Hours per week today minus hours per week after) × fully loaded hourly cost × 52.
- Error value
- Errors per month × cost of each error × 12.
- Year-one net return
- Time value + error value − year-one cost (software, setup and training).
- Payback in months
- Year-one cost ÷ ((time value + error value) ÷ 12).
A worked example
A process takes 10 hours a week today and would take 3 after automation. The people doing it cost $40 an hour fully loaded. The time value is 7 hours × $40 × 52, or $14,560 a year. With a year-one cost of $8,000 and no error savings counted, the year-one net return is $6,560 and payback is about 6.6 months.
That is a typical example, not a client result. Run it with your own numbers, and add the ongoing cost per year to see what year two returns.
Saved hours are not savings yet
Saved hours become savings only when they go somewhere. Before funding the build, decide where the team's time will go: more clients served, faster replies, the work that has been waiting. Otherwise the hours dissolve into the week and the value case never shows up in the numbers.
What usually gets left out
Errors and upkeep. The cost of errors is often larger than the time value and is rarely counted, because nobody tracks the follow-up that did not happen. Upkeep runs the other way: integrations need monitoring and subscriptions renew, so year two has a cost too.